A 35 kV oil-immersed transformer connects utility, industrial and renewable-energy systems across a wide range of capacities. Because each project has different network and site conditions, the factory design should not start from voltage and kVA alone.
Clear technical data at the beginning reduces drawing revisions, protection changes and civil rework. The purchase specification should identify the guaranteed performance and the physical interfaces the supplier must meet.
Electrical Data That Drives the Design
Confirm rated power, frequency, primary and secondary voltage, highest system voltage, insulation level, vector group, neutral arrangement and tap range. The network study should provide the required impedance and short-circuit withstand duty.
Loss evaluation should distinguish no-load loss, load loss, auxiliary consumption and the economic value assigned to each. A low purchase price may not be the lowest lifecycle cost when the transformer is energized continuously.
Mechanical and Accessory Checklist
Define ONAN or ONAF cooling duty, temperature-rise limits and fan-control stages.
Confirm bushing type, terminal orientation, cable boxes or bus connections and phase spacing.
Specify conservator or sealed-tank arrangement, oil-preservation system and pressure protection.
List gauges, alarms, contacts, marshalling cabinet, CTs and online monitoring points.
Provide transport limits, lifting and jacking points, total mass and shipping configuration.
Coordinate foundation loads, oil containment, fire separation, earthing and maintenance clearances.
Approve Documents Before Materials Are Committed
The review package should include a general arrangement, nameplate data, terminal plan, control schematic, accessory list, foundation loads and guaranteed-loss schedule. Comments must be resolved consistently across electrical and civil drawings.
Factory test scope, witness points, report format and spare parts should be agreed before production. This keeps the final inspection focused on requirements that were defined, priced and engineered from the start.
Next Step
SOVIN’s máy biến áp phân phối ba pha ngâm dầu supports project-specific voltage, tapping, impedance and accessories. Provide the single-line diagram and site data with the inquiry.
Technical reference: IEC 60076 series and the project’s applicable grid-code and substation requirements.
Trước khi lựa chọn thiết bị cho dự án của bạn, hãy so sánh các loại máy biến áp khô và máy biến áp ngâm dầu dựa trên các tiêu chí như hệ thống làm mát, lắp đặt, bảo trì, an toàn phòng cháy chữa cháy, hiệu suất và ứng dụng.
Việc nâng cấp trạm biến áp công cộng không chỉ đơn thuần là tăng công suất máy biến áp. Thiết bị còn phải đảm bảo khả năng chuyển đổi điện áp ổn định, kế hoạch bảo trì có thể dự đoán được và tích hợp an toàn với các hệ thống bảo vệ hiện có. Trường hợp ứng dụng này trình bày tóm tắt...
Grid connection queues are becoming a central issue for power-system developers. The International Energy Agency’s Electricity 2026 report says more than 2,500 GW of renewable generation, storage and large-load projects are waiting in connection q...
Fast-charging networks are increasing both the number and the power rating of public charging points. The International Energy Agency’s Global EV Outlook 2026 reports that fast and ultra-fast chargers grew from 1.5 million in 2024 to 2.2 million i...
Gửi yêu cầu tư vấn về sản phẩm
Chúng tôi sẽ liên hệ với quý khách trong vòng 24 giờ